| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Course Introduction | 1 day | Wed 1/10/01 | Wed 1/10/01 | johnmc | 100% |
| 2 | Product Planning | 6 days | Wed 1/17/01 | Wed 1/24/01 | johnmc,individual students | 100% |
| 3 | Feasibility Study Due | 1 day | Wed 1/24/01 | Wed 1/24/01 | individual students | 100% |
| 4 | Project Planning/Scheduling | 6 days | Wed 1/24/01 | Wed 1/31/01 | johnmc,individual students | 100% |
| 5 | Process and Schedule Due | 1 day | Wed 1/31/01 | Wed 1/31/01 | individual students | 100% |
| 6 | Product Requirements | 6 days | Mon 2/5/01 | Mon 2/12/01 | johnmc,project teams | 0% |
| 7 | Requirements Model Due | 1 day | Mon 2/12/01 | Mon 2/12/01 | | 0% |
| 8 | Domain/App Analysis | 6 days | Mon 2/12/01 | Mon 2/19/01 | johnmc,project teams | 0% |
| 9 | Analysis Model Due | 1 day | Mon 2/19/01 | Mon 2/19/01 | | 0% |
| 10 | Requirements Iteration 2 | 1 day | Wed 2/21/01 | Wed 2/21/01 | | 0% |
| 11 | Architectural Design | 6 days | Wed 2/21/01 | Wed 2/28/01 | | 0% |
| 12 | Requirements Iteration 3 | 1 day | Wed 2/28/01 | Wed 2/28/01 | | 0% |
| 13 | Analysis Iteration 2 | 1 day | Wed 2/28/01 | Wed 2/28/01 | | 0% |
|